Saturday, October 11, 2008

Set out


Set out for the house being constructed started at 10.45 A.M on 11,October,2008 and completed by 12.45 P.M

We have started set out using the original lines made for stone laying by keeping the stone laid in the South West corner of the building

As 2.53 meters is left in the rear side originally while laying the stone,one wall will come very close to well therby necessiating removal of well before completion of the foundation work.
One more small tree has to be removed and Electrical switch board has to be shifted to rear compound wall side for earth work excavation work

Picture shows commencement of set out work