Tuesday, October 28, 2008

Foundation rubble work completed


Foundation rubble work in dry pack is completed except for the forced filling of quarry dust into rubble work which could not be done due to non availability of Electric motor and water.A few loads of rubble,One load of river sand half completed workers shed are remaining at site

a house is taken on rent nearby for staying of workers and that is now being left locked paying rent due to stoppage of work

.Picture shows Foundation rubble work